Global TD-LTE Initiative
Task-T-PM2-PJ5-2: Device test equipment

Leader

Feng Xiang Keysight
Shi Xiaofeng R&S
Choi Bosco Anritsu

2017

Objective

1. Conformane test:
- Requirement definition
- Draft specification.
- Prototype availabe
- Intial test started

2. Performance test:
- Requirement definition
- Draft specification

3. OTA test:
- Requirement definition
- Draft specification

Work plan

Q1

for Objective 1:
1.1. Test requirements:
- to get draft key RF spec for initial design of test method;
- to get the collaboration partner list inside this task, operator/BTS vendor company/test device vendor company…
- to get more input related with RF spec from project 1&2
1.2. Test case spec:
1.3. Test equipment:
- Preparation

for Objective 2:
Investigatiton
to get the collaboration partner list inside this task, operator/BTS vendor company/test device vendor company…

for Objective 3:
Test requirements and methodology Investigation

Q2

for Objective 1:
1.1. Test requirements:
RF test: darft document for requirements definition available.

for Objective 2:
Signaling tests: requirements investegation starts.
1.2. Test case spec:
RF part step 1: An incomplete document designed to guide discussion and generate feedback, and may include several alternative solutions for consideration.
1.3. Test equipment:
step 1: Techniqual report with information clollection from instrument vendors for proposal platforms / resources / …

for Objective 3:
Test Requirement specs

Q3

for Objective 1:
1.1. Test requirements:
RF test: requirements document release.

Signalling/RRM test: draft document avaialable.
1.2. Test case spec:
RF part step 2: A document in Spec format. Drafts are susceptible to substantial change during the review process.

Signaling part step 1: Incomplete document to guide discussion.
1.3. Test equipment:
step 2: Report of draft design for prototype.

for Objective 2:
Draft Test requirements
Test cases investigation

for Objective 3:
Test case specs

Q4

for Objective 1:
1.1. Test requirements:
Signalling/RRM test: requirement document relase.
1.2. Test case spec:
RF part step 3: A generally public documents available for testing.

Signaling part step 2/3: Public documents are available.
1.3. Test equipment:
step 3: Design and implement prototype.

for Objective 2:
Test requirements documentation
Test cases definition
Test equipment development

for Objective 3:
Test eqipment developing

2018

Objective

1. Conformane test:
- Test platform ready
- Trial test with device vendors
2. Performance test:
- Test platform development and integration
- Trial test with device vendors
3. OTA test:
- Trial test with device


Work plan

Q1

for Objective 1:
Test platform protype development

for Objective 2:
Test platform protype development

for Objective 3:
Test eqipment developing

Q2

for Objective 1:
Prototype ready and integration with device.

for Objective 2:
Test prototype system integration

for Objective 3:
System integretation and test

Q3

for Objective 1:
RF trial tests available.
Signaling tests integration.

for Objective 2:
Prototype ready and integration with device.

for Objective 3:
System integretation and test

Q4

for Objective 1:
Signaling/RRM trial tests.

for Objective 2:
Trial tests with device, RF part.

for Objective 3:
Trial tests with device vendors