Objective

Develop the 5G terminal requirements and device features capability based on 3GPP discussion.

Work plan

Q1

Skeleton of initial feature candidates of 5G terminals based on 3GPP NR SI. [For example, UE impact of SA & NSA, UL MIMO, SAR and OTA test, voice solution and other issues.]

Q2

Update feature list based on 3GPP discussion. [For example, the issues need to be identified and fix the skeleton of the study report.]

Q3

Complete of whitepaper on pre-commercial device feature list.

Q4

Complete of whitepaper on pre-commercial device feature requirements.

2018

Objective

Complete the performance requirments, test case, and validation method.
And technology requirments update.

Work plan

Q1

1. Skeleton the performanc requiremtns and test spec based on 2017 feature requiremnts.
2. Skeleton of update feature listed based on 3GPP discussion.

Q2

2nd update on feature list based on 3GPP discssion.

Q3

Complete GTI whitepaper of pre-commercial device feature list.

Q4

Complete GTI whitepaper on pre-commercial device performance requirments, and 1st draft of and test spec.

2019

Objective

1. Complete the performance requirements test case, and validation method.
2. Pre-commercial devices promotion.

Work plan

Q1

Q2

Draft the 2nd edition of pre-commercial device performance requirments and test spec.

Q3

Demo, and update the pre-commercial device lab/field test result.

Q4

Complete the 2nd edition of GTI whitepaper on pre-commercial device summary report.